Bengaluru Metro Blue Line Begins Trials, Eyes Mid-2027 Opening

By The Indus Pulse Editorial Team3 min read
A modern elevated metro train traveling on a concrete viaduct through a sprawling city with skyscrapers
Illustrative imageIllustrative library image, not taken at the event

Trial runs on the Phase 2A section of Bengaluru's Namma Metro Blue Line along the Outer Ring Road started from KR Puram on Tuesday, November 24, 2026, with public operations targeted for mid-2027, Greater Bengaluru Development Minister Krishna Byre Gowda said, according to NDTV and The Indian Express. Gowda rode a trial train from KR Puram to Doddanekkundi and inspected Doddanekkundi Metro Station, noting that testing covers the first four stations toward Mahadevapura this month and will expand to four more stations next month, NDTV and Metro Rail News reported. The Phase 2A corridor between KR Puram and Central Silk Board comprises 13 stations, with NDTV citing its length as 19 km while Metro Rail News and The Indian Express put it at 19.75 km.

Signalling Timeline and Construction Progress

Bangalore Metro Rail Corporation Limited (BMRCL) reported that piling, pier construction, U-girder casting and erection works are complete, 37.1 km of the 39.2 km of tracks have been laid, 85 per cent of station entry and exit works are done, and 68 per cent of roofing is finished, The Indian Express reported. Gowda said installation of the automatic signalling system is expected to finish by January, followed by mandatory Commissioner of Metro Railway Safety (CMRS) inspection and certification starting after February, putting the full testing and approval timeline at seven to eight months. Along the Outer Ring Road, where an estimated 11-12 lakh people work, Gowda said the line is intended to ease severe road congestion. Planning for Phases 2A and 2B began in 2016-17, Cabinet approval came in 2017 and construction started in 2020, he said. For Phase 2B, particularly the KR Puram-Hebbal stretch, officials have been told to speed up work with contractors so the entire 58.2-km Blue Line from Central Silk Board to Kempegowda International Airport, estimated at around Rs 20,000 crore, is completed within one-and-a-half years or by 2028, NDTV and The Indian Express reported. In January 2025, BMRCL estimated daily ridership for the Blue Line at 7.7 lakh passengers, Bangalore Mirror reported at the time. Officials expect space constraints at Byappanahalli depot, which will support train operations on the airport line, to be resolved by February, allowing more trains to be inducted and accommodated, according to The Times of India.

Funding Pressures, Fare Stance and New Proposals

Gowda said foreign exchange shifts, with the dollar rising from around Rs 70-80 at borrowing to roughly Rs 100, added nearly 30 per cent to loan repayment burdens, while approval delays raised material costs, though the State has provided funds to avoid cash delays, NDTV reported. He said the Metro corporation records an annual loss of around Rs 600-700 crore including depreciation, or an operating surplus of Rs 50-60 crore excluding depreciation, and stressed that no decision has been taken to hike ticket fares. Gowda also said the State is awaiting Union Government approval for its Red Line expansion nearly 22 months after submitting a request to Prime Minister Narendra Modi, has proposed a double-decker corridor from Sarjapur through Ibbalur Junction to St John's, and is targeting a 176-km network by 2027 and 500 km by 2037, NDTV and Metro Rail News reported. The Asian Development Bank's project page lists a US$500 million loan (4036-IND) from its ordinary capital resources and US$330.42 million from the Japan International Cooperation Agency for the Bengaluru Metro Rail Project. The Times of India reported a higher figure for the last financial year: BMRCL's loss before tax surged to Rs 1,717.4 crore from Rs 691.6 crore, primarily because finance costs more than tripled to Rs 1,793 crore.