July 13, 2026 at 01:59 PM 2 min readindiadeveloping

Telangana Accelerates Devadula Irrigation Project Completion

Devadula Project Push:

The Telangana government has prioritized the completion of the Devadula Lift Irrigation Project, with leadership declaring a war-footing approach to finish all pending works. Irrigation Minister Uttam Kumar Reddy has formally set a deadline of December 31, 2027, for full operational capability. Deputy Chief Minister and Finance Minister Bhatti Vikramarka has guaranteed that financial constraints will not impede progress, as the administration seeks to utilize the project's total capacity of 38.16 TMC to secure irrigation for regional farmers.

Progress and Challenges:

As of May 2026, the ambitious irrigation endeavor had reached 87.70% physical completion, with a total expenditure recorded at ₹14,422 crore. An additional ₹3,978 crore is estimated as necessary to finalize the remaining infrastructure. The project’s timeline has faced significant delays, primarily driven by complex land acquisition requirements and technical challenges related to canal lining. Despite these hurdles, the government recently initiated continuous water pumping from the Godavari River to mitigate drought conditions across the erstwhile Warangal district.

Operational Outlook:

Currently, seven of the ten installed pumps are fully operational, with engineers working to activate the remaining three units shortly. The ongoing water diversion efforts aim to fill critical local reservoirs including Dharmasagar, Station Ghanpur, Nawabpet, Ashwaraopally, Chitakoduru, and Bommakur. Successful completion of this infrastructure is expected to provide assured irrigation for approximately three lakh acres of agricultural land, significantly bolstering the rural economy of Telangana. The focus remains on resolving lingering bottlenecks in canal lining to reach the full operational capacity by the 2027 deadline.
Pulse Intelligence
AI Analysis
  • The project aims to utilize a capacity of 38.16 TMC to provide irrigation to approximately three lakh acres in the Warangal district.
  • As of May 2026, physical progress stood at 87.70% with ₹14,422 crore already invested.
  • Completion of canal lining and land acquisition remains the primary hurdle for the 2027 project deadline.
  • Full activation of all ten pumps will significantly increase the volume of Godavari water available for local reservoirs.
  • Assured irrigation for three lakh acres is expected to stabilize agricultural output in the drought-prone Warangal region.